San Pedro Water & Sewerage Project

Period: October 1994 - January 1996
Contract: San Pedro Water & Sewerage Project.
Contract A.
Reservoir.
Sewerage Stabilization Ponds/Access Road
Country: Belize
Employer: Johnston Int'l Ltd.
Employer's Address: P.O. Box 70
Providenciales
Turks & Caicos Island British West Indies Tel: 809-946-4279
Nature of Works:

A. Reservoir.
Construction of a .5 million gallons concrete water reservoir on a piled foundation.
Salient Points are:
-40 plus concrete piles (5,500 p.s.i.) were constructed, driven
and capped.
-622 cubic meters of 35 mpa concrete was poured.
-93 tonnes of rebar was bent and placed.
-318 square meters of 295 cm and 143 cm blocks placed

Contract Period – 9 months.

B. Sewerage Stabilization Pond/Access Road
1,400m long, 6m wide access road was constructed as an access road to construct a 30 acre sewerage pond. The road and ponds were constructed on reclaimed mangrove landusing locally available fill on the island.

Role: Sole Contractor
Total Value of Contract: BZ $5,179,000.00
(US $2,589,500.00)
Contract Awarded:
Period:
Completion Date: January 1996.
Funding Agency:

Description: